Mega-First’s RISKY investment threatens future of Mekong

by Team FNVA
A+A-
Reset

KATE ROSS
The Nation
May 22, 2015

High-risk overseas investment projects are a growing concern for responsible business. Mega-First Corporation Berhad is likely to come under fire at its annual general meeting today, as the company faces growing criticism for its role in the controversial Don Sahong Dam, planned on the Mekong River in Laos.

Mega-First, the Malaysian project developer, has pushed forward on implementation of the Don Sahong Dam – the second Mekong mainstream dam – despite opposition from the Cambodian, Thai and Vietnamese governments, and calls for further study of the project’s impacts.

The company’s disregard for the concerns of neighbouring governments, the rights of Mekong communities and the procedures for regional cooperation in the Mekong, has raised alarm over Mega-First’s involvement in a project which, for only 260MW of electricity, risks jeopardising the food security and lives of millions of people throughout the Mekong region.

The location of the Don Sahong Dam in Siphandone, southern Laos, is a unique microcosm of the Mekong River’s rich ecosystem. The area is renowned for abundant fisheries that support more than 200 species of fish, which act as a staple in the diet and livelihoods of local communities.

The Don Sahong Dam will block the main channel used year round by fish migrating between Mekong countries. Disrupting fish passage will have a profound and irreversible impact on food security and lives throughout the region.

The project is also positioned just one kilometre from the core habitat of a group of critically endangered Irrawaddy Dolphins, and less than two kilometres from the Cambodian border.

Despite warnings from experts, and requests from Mekong governments and communities, Mega-First has never adequately studied the dam’s transboundary impacts.

Thai, Cambodian and Vietnamese people have publicly opposed the project and appealed to Mega-First to halt construction through letters, petitions and peaceful protests. A petition signed by more than 50,000 people, organised by the World Wildlife Fund, was sent to Mega-First’s executive chairman, urging him to put a stop to the project. However, so far the concerns raised to Mega-First have fallen on deaf ears.

In October 2014, six NGOs filed a complaint with the Malaysian Human Rights Commission against Mega-First for its role in the Don Sahong Dam. The complaint, filed on behalf of communities in Cambodia and Thailand, highlights the failure of Mega-First to understand the likely impacts of the project and take action to minimise its harm on local communities. By failing to inform or consult with communities that will be affected by the project, Mega-First has operated against the principles of international law.

By moving ahead with construction of the Don Sahong Dam, Mega-First is also disregarding the procedures for regional cooperation between lower Mekong governments. The four governments have not been able to reach agreement about the future of the project. At a meeting of the Joint Committee of the Mekong River Commission in January 2015, it was decided that the inter-governmental decision would be raised to a ministerial level. However, this meeting has not happened, and yet construction at the dam site continues.

While Mekong countries await further study in order to assess the project’s impacts beyond the borders of Laos, questions remain regarding the project’s proposed mitigation measures, which have never been proven to work in the Mekong. As the sole project developer, it is Mega-First’s responsibility to bear the burden of proof, something that the government of Vietnam reiterated in January. Existing studies remain insufficient to demonstrate the project’s success, or who will bear the responsibility and cost should the mitigation measures fail.

It is clear that many uncertainties remain in understanding the far-reaching impacts of the Don Sahong Dam, and in plans to mitigate these impacts. To continue to implement the dam in this way is highly irresponsible and risks not only the food security and livelihoods of millions of people in the Mekong region, but also the future of regional cooperation.

Mega-First still has the opportunity to choose a different path, and to demonstrate it is a responsible and ethical company, thereby ensuring its own reputation as well as the future of a sustainable Mekong River.

A first step towards responsible action will require Mega-First to immediately stop all construction towards the Don Sahong Dam and carry out comprehensive baseline studies, transboundary impact assessments, and meaningful consultation with affected communities in all lower Mekong countries.

KATE ROSS is Mekong Programme associate for International Rivers, a US-based international organisation working to protect rivers and the rights of people who rely upon them.